Why Changes Are So Costly

Jim Schneider • September 4, 2026

Why Changes Are So Costly

Change orders almost always mean a bigger budget and a longer schedule, and most of them trace back to decisions that were never fully made.


With prices showing up in the news and at the grocery store, homeowners keep asking what they can do to keep construction costs from climbing. A good part of the answer is simple. Choose the features and products you want before the work begins, then hold changes to a minimum.


That has always been sound advice. Supply timelines and price trends make it more important now.


Builders dislike change orders for good reason. A product or detail altered after work starts nearly always costs more than the same product chosen and planned for during design. Changes also disrupt a schedule that was built around a sequence.


Say a homeowner decides to add a couple of decorative beams to the family room ceiling. They are nonstructural and carry no load from the floor above, but they still have to be supported, so the framers come back to add blocking in the ceiling cavity above the drywall. The electrician may need to move recessed lights so they center between the new beams.


Or picture a walkthrough after plumbing and electrical rough-in, when a counter-mounted faucet suddenly looks better than the wall mount that was specified. It seems like a small change. The plumber has to be called back, wires and boxes may have to move, and if the inspector has already signed off on the rough plumbing, another inspection gets scheduled. Drywall and cabinets wait behind all of it.


That is where the real cost hides. It is rarely the price of the faucet. It is the return trips, the resequencing, and the days a house sits idle waiting on one trade to come back. Skilled subcontractors are booked months out, and a crew that has moved on to another job cannot break away for a twenty-minute fix. Specialty and coastal-grade items are ordered, not pulled off a shelf, so substituting one mid-project can reset a lead time by six weeks.


Costs for residential building materials also continue to climb, according to the National Association of Home Builders. The latest Producer Price Index from the U.S. Bureau of Labor Statistics puts residential building material prices 5 percent above where they stood a year ago, the steepest annual increase since December 2022. Softwood lumber alone is up more than 17 percent. Making selections early remains one of the most reliable ways to protect both a budget and a completion date.


The fix is not discipline on the homeowner's part. It is process. A well-run project settles selections during design, while a change costs nothing but a conversation. Lead times get confirmed before the schedule is built, not after. Allowances carry real numbers tied to products the homeowner has actually seen, rather than placeholders that guarantee a decision gets pushed into the framing stage. Homeowners who walk into construction with those items closed out spend the build watching progress instead of making calls.


Ask any builder how selections are handled before the contract is signed. If the answer is that they get sorted out as the job moves along, expect change orders. If the answer describes a selections schedule with deadlines attached to each trade, that is a project built to hold its number.


None of this is an argument against changes. It is your home, and if getting what you want requires a change, make it. The point is understanding what a change sets in motion, so the decision is made with the full picture in view.


Costs for residential building materials also continue to climb, according to the National Association of Home Builders. The latest Producer Price Index from the U.S. Bureau of Labor Statistics puts residential building material prices 5 percent above where they stood a year ago, the steepest annual increase since December 2022. Softwood lumber alone is up more than 17 percent. Making selections early remains one of the most reliable ways to protect both a budget and a completion date.


The fix is not discipline on the homeowner's part. It is process. A well-run project settles selections during design, while a change costs nothing but a conversation. Lead times get confirmed before the schedule is built, not after. Allowances carry real numbers tied to products the homeowner has actually seen, rather than placeholders that guarantee a decision gets pushed into the framing stage. Homeowners who walk into construction with those items closed out spend the build watching progress instead of making calls.


Ask any builder how selections are handled before the contract is signed. If the answer is that they get sorted out as the job moves along, expect change orders. If the answer describes a selections schedule with deadlines attached to each trade, that is a project built to hold its number.


None of this is an argument against changes. It is your home, and if getting what you want requires a change, make it. The point is understanding what a change sets in motion, so the decision is made with the full picture in view..

It Takes a Village

We had a record turnout at our Summer Vendor Breakfast! Hear from our trades and suppliers about what makes working with us different by clicking HERE.


Ask the Builder:

Q: The building code says the crawl space is supposed to be vented. Is that right?

A: It is allowed by code. That does not make it a good idea. Foundation vents assume outside air will dry the space out, but in Coastal Virginia during July, outside air is the problem. Air at 95 degrees and 90 percent humidity meets framing and ducts sitting in the mid-60s and gives up its moisture on contact. The vents aren’t drying the crawl space, they’re feeding it. And it does not stay down there; air moves up through the house, which is why a home can run its air conditioner all day and still feel damp.


The fix is to stop treating the crawl space as outdoors. Seal the vents, run a vapor barrier across the ground and up the walls, insulate at the foundation walls, and add a dehumidifier with a drain. A sealed crawl space without a dehumidifier is just a sealed box. The barrier and the dehumidifier are one system.

By Jim Schneider August 4, 2026
Who You Gonna Call?
By Jim Schneider July 13, 2026
Health and Comfort, Engineered In
By Jim Schneider June 29, 2026
The Super Secure Luxury Home | BIS 2026 St. Louis
By Jim Schneider June 8, 2026
Why Sharing Your Budget Leads to a Better Home
By Jim Schneider April 15, 2026
A Home for All Ages
By Jim Schneider April 7, 2026
A Coastal Jewel Awaits on the Chesapeake Bay
By Jim Schneider March 30, 2026
Why You Should Hire a General Contructor
By Jim Schneider March 20, 2026
And why “price per square foot” is one of the most misleading numbers in residential construction. One of the most common questions we receive is: “How much do your homes cost per square foot?” It’s a reasonable question — but for a true custom home, it’s the wrong metric. Custom homes are not mass-produced products. They are built once, on one specific piece of property, for one specific family. Unlike production homes, there is no repeatable formula where square footage alone determines price. Too many critical cost drivers have nothing to do with the size of the house. Design Drives Cost — Not Just Size Two homes can be 3,000 square feet and differ by hundreds of thousands of dollars. Why? Ceiling heights and roof complexity Window quantity, size, and performance level Structural engineering requirements Finish selections (flooring, cabinetry, tile, appliances) Exterior materials (brick, siding, stone, trim detail) Mechanical system sophistication A simple rectangular footprint costs far less than a home with multiple rooflines, structural beams, and large glass openings — even if the square footage is identical. And if a builder chooses to build high-performance homes with advanced insulation systems, geothermal HVAC, air sealing strategies, and verified performance testing, those investments improve durability and comfort — but they do not increase square footage. The Lot Can Change Everything Where you build often impacts the budget more than what you build. Slope, soil conditions, water table levels, and accessibility can dramatically alter excavation and foundation costs. Building on the Eastern Shore versus an urban infill lot in Hampton Roads comes with very different regulatory and infrastructure requirements. Utility tap fees, well and septic systems, long service trenches, stormwater management, flood zone requirements, and permit costs all vary by jurisdiction. Some municipalities require thousands — even tens of thousands — of dollars in impact and utility fees before construction even begins. These costs have zero connection to the home’s square footage. Regulations & Community Requirements HOA guidelines, architectural review boards, and local code requirements can mandate specific materials or construction methods. Coastal zones may require additional structural upgrades, elevated foundations, or moisture management strategies. Again — none of this shows up in a square foot calculation. Why Square Foot Pricing Falls Apart Square foot pricing works in production housing because every home is nearly identical. Custom homes are different. They are shaped by design complexity, site conditions, regulatory environments, performance goals, and homeowner priorities. If someone offers you a “ballpark” price per square foot without understanding these variables, that number is little more than a guess. A custom builder will invest significant time in preconstruction to understand your design, your lot, and your performance expectations. That’s how we create budgets that are accurate — not just convenient. Because in a custom home, value isn’t measured by square footage. It’s measured by how well the home is designed, built, and performs for decades to come. Warm Regards,
By Jim Schneider March 20, 2026
Recently, Jim Schneider of Schneider Construction joined Seth Kelley of MCG Homes on The Punch List Podcast to discuss one of the most important drivers of success in custom homebuilding and remodeling: building strong relationships with trade partners. During the conversation, Jim shared insights from his experience building custom homes in Cape Charles, Virginia, highlighting how long term success in the industry depends on trust, communication, and consistency with the trades that make each project possible. Together, Jim and Seth explored what separates builders that trades want to work with from those they avoid. The discussion covered everything from jobsite culture and clear expectations to accountability and mutual respect between builders and their trade partners. For Schneider Construction, these relationships are foundational. A well run project is the result of a team effort, and strong partnerships with skilled trades ensure that every home is built with the level of craftsmanship and care clients expect. If you’re interested in the business side of custom homebuilding and the importance of maintaining strong trade relationships, this episode offers practical insights into how builders can create better working partnerships and stronger projects. Be sure to tune in to the next episode as the conversation continues with a deeper look into another key piece of the puzzle: building strategic relationships with suppliers.
By Jim Schneider November 11, 2025
If you’re considering building a custom home in Cape Charles, you’ve likely heard the term “high performance home.” But what does that really mean? And why does it matter for your lifestyle on Virginia’s Eastern Shore?